Mrs Daniel’s property an illegal structure, says Ogun govt

7 min read
0
0
142

Ogun State Government said on Sunday that DATKEM Plaza, Ijebu Ode is an illegal structure without an approved plan.

According to the state government, the structure also contravened its physical planning laws.

In the early hours of the day, the state government had demolished the structure, which belongs to Mrs Olufunke Daniel, wife of former governor of the state, Senator Gbenga Daniel.

But in the statement by the Permanent Secretary in the state’s Ministry of Physical Planning and Urban Development, Engr. Olayiwola Abiodun, the government said the structure violated the building codes of the state and had numerous defects.

The structure, the state government added, also contravened the state’s physical planning laws.

He said several efforts made by the state government to halt further development on site were ignored by the developers.

He said government officials requested the structural engineer in charge of the building to avail the state of the structural equilibrium of the building, a request, he said, was ignored.

The statement recalled the various incidences of building disasters across the country, adding that the state government would not fold its arm and allow and such occurrence.

It noted that many of such disasters, such as fire outbreaks at Ikorodu, led to the loss of precious lives.

According to the Permanent Secretary, what the government did in partially pulling down the defective building was to be proactive.

Abiodun challenged the owners of the structure to produce evidence of government approval in their possession.

He said that, for a commercial building of that status, there must be parking space to accommodate vehicular traffic within and outside the facility for workers and visitors. He explained that the provision of the law is for 45 to 50 per cent of available land for construction as a buildable area.

Abiodun further said that the building lacked stage certification, which is usually issued at every stage of construction.

He said that the owners were served the necessary notices, including abatement, contravention, stop work and demolition between May and October 2022, which, according to him, were ignored.

According to the statement, DATKEM Enterprises Limited submitted application for an office building, located along Ibadan Road, Ijebu Ode in 2009 with registration number CB/05/299/2009.

The statement further read: “The proposal was for five (5) floors with airspace of three metres at the right, five metres at the left, five metres at the rear and a setback of 32.5516 metres to the middle of Ijebu Ode/Ibadan road, Ijebu-Ode.

“The Zonal Town Planning Office observed during routine monitoring that the construction on site did not conform with the plan granted as there was a deviation from the airspaces and setback.

“In addition, the building had been modified and enlarged with an additional storey building at the back thereby becoming over density.

“In view of the above, the following actions were taken:

“Contravention Notice with Serial No. 0106983 was served on 24th May 2022.

“Stop Work Order with Serial No. 000623 was served on 24th May 2022.

“Another Stop Work Order with Serial No. 001065 was served on 22nd July 2022 when the first notice was ignored.

“Demolition Notice with Serial No. 0007549 was served on 11th October 2022.

“Notice to seal with Serial No. 000815 was served on 4th October 2022″.

The statement noted further that despite all these notices, the developer was recalcitrant and continued with the construction work.

It continued: “This prompted the re-sealing of the site on 1st August 2023. But the sealing did not stop the developer from further construction as work continued on the site.

“However, the developer wrote an appeal for unsealing, which was considered so as to evacuate the belongings in the premises. Thereafter, quit notice with Serial No. 0030750 was served on 31st August 2023.

“In view of the above, since the developer had remained recalcitrant, the Zonal Town Planning Office’s recommendation for the demolition of the office building was upheld”.

The state government reiterated its commitment to ensure the safety of its citizens, adding that any defective buildings in any part of the state will be demolished to safeguard the lives of the people.

Load More Related Articles
Load More By Breezynews
Load More In Property

Leave a Reply

Your email address will not be published. Required fields are marked *

Check Also

CCTV cameras will be installed on Lagos-Calabar coastal highway – Umahi

The federal government has disclosed plans to install Closed Circuit Television cameras (C…