The Transmission Company of Nigeria (TCN) said its maintenance crew has fixed the Jos-Lafia 330kV transmission lines, which it said had been redundant for some time.
It was gathered that TCN on Saturday commenced what it called a ‘scheduled preventive maintenance’ on the Jos-Lafia 330kV transmission lines 1 and 2.
The seven-hour scheduled preventive maintenance commenced today and it was scheduled to end by 4 pm.
The TCN said customers of the Jos Electricity Distribution Company in Bauchi would not be affected by the maintenance.
A statement by the TCN Public Affairs General Manager, Ndidi Mbah, noted, “Since the Jos-Lafia transmission lines have been redundant for a while, Jos DisCo has been duly informed that there would be no load loss”.
According to Mbah, Bauchi will get electricity supply from Kaduna-Jos 330kV lines.